Prime Cost Items vs Provisional Sums: What’s the Difference?

Building contract page explaining provisional sums and prime cost items, with a pen, calculator and plans

If you’re comparing building proposals or reading through a building contract, you’ll probably come across the terms Prime Cost Item and Provisional Sum.

They can look similar because both are allowances rather than fixed prices, but they are used for different things.

Understanding the difference is important, because these allowances can have a significant effect on the final cost of your build.

What is a Prime Cost Item?

A Prime Cost, or PC, item is generally an allowance for a fixture or fitting that has not been finally selected when the contract is prepared.

Typical examples might include:

  • tiles
  • tapware
  • sanitaryware
  • appliances
  • sinks
  • basins
  • other selected fixtures or fittings

For example, your contract might include an allowance for tiles based on a certain amount per square metre.

That doesn’t necessarily mean you have to choose a tile at exactly that price.

You might select a more expensive floor tile and a less expensive wall tile, with the overall selection still sitting reasonably close to the allowance.

The important part is that the PC amount is an allowance, not necessarily the final cost of the product you eventually choose.

If your selections cost more than the allowance, the contract price will generally increase by the difference. If they cost less, there will generally be a corresponding credit, subject to the terms of your contract.

What is a Provisional Sum?

A Provisional Sum, or PS, is slightly different.

Rather than being an allowance for a particular fixture or fitting, it is an estimated allowance for a section of work where the exact cost cannot reasonably be determined when the contract is prepared.

This can happen because the final scope, quantity or construction method is not yet known.

Examples could include certain site works, landscaping or work that depends on conditions that won’t be fully understood until construction progresses.

A provisional sum normally allows for the work as a whole, including the labour and materials associated with that particular item.

Once the actual work has been completed and its real cost is known, the contract price can then be adjusted accordingly.

The easiest way to remember the difference

A simple way of looking at it is:

Prime Cost Item = something you are going to select.

Provisional Sum = work we cannot accurately price yet.

That’s not a complete contractual definition, but it’s a useful way of understanding why the two allowances appear in a building proposal.

Why do builders use allowances at all?

Ideally, as much of a project as possible would be completely selected, designed and priced before the contract is signed.

In the real world, that isn’t always practical.

You may not have chosen every tap, basin or tile yet.

There may also be parts of the work where more information is required before an exact cost can be established.

Allowances let the project move forward without pretending that an unknown cost is already fixed.

Used properly, they are a perfectly normal part of building.

The important thing is that they are realistic.

Why the size of the allowance matters

This is where homeowners need to pay attention when comparing building proposals.

Two builders can appear to be pricing the same house, but one proposal may contain much lower allowances than the other.

That can make the initial contract price look cheaper without necessarily making the finished house cheaper.

For example, if one proposal contains a realistic tile allowance and another contains an allowance that is well below the type of tile you are likely to choose, the cheaper proposal may simply create a larger adjustment later.

The same principle applies to provisional sums.

A low provisional allowance doesn’t make the underlying work cost less.

It simply means less of the likely cost has been included in the original contract amount.

Look beyond the bottom line

When comparing building proposals, don’t just compare the total price.

Look at:

  • what is actually included
  • what is excluded
  • the value of each PC allowance
  • the value of each provisional sum
  • whether those allowances suit the level of finish you are expecting
  • how much of the project is genuinely fixed and how much remains uncertain

This is one of the reasons two building proposals that appear to cover the same project can have very different totals.

Sometimes the difference isn’t the builder’s price at all.

It is simply the amount of the finished project that has actually been allowed for.

Can you reduce the number of PC items and provisional sums?

Often, yes.

The more decisions that can be made before the contract is finalised, the more accurately the project can usually be priced.

Finalising things such as finishes, fixtures and specifications earlier can reduce the number of Prime Cost allowances required.

Likewise, completing the necessary design, engineering and investigation work before construction can sometimes reduce the number of Provisional Sums.

There will always be circumstances where allowances are appropriate, particularly with renovation work where parts of the existing building may remain concealed until construction starts.

But generally, the fewer genuine unknowns there are, the clearer the final construction price becomes.

Our approach

At Fortress Construction WA, we prefer to resolve as much information as reasonably possible before construction begins. That is what our design and build process is set up to do, and it is why every proposal starts from our Foundation Specification.

That means working through the design, specification, selections and construction details early, rather than relying on an artificially low starting figure and sorting everything out later.

There will always be some decisions that need to be made during a project, and occasionally some things simply cannot be known in advance.

When allowances are required, however, they should make sense for the project and the level of finish being discussed.

Because ultimately, a building proposal is only useful if it gives you a realistic understanding of what your completed project is likely to cost.

The takeaway

Prime Cost Items and Provisional Sums are not hidden charges.

They are simply ways of dealing with costs that haven’t been completely finalised when the contract is prepared.

The key is understanding what they represent and whether the allowances included in your proposal are realistic.

If you are comparing building proposals, spend some time looking at the allowances rather than concentrating solely on the final number.

It can tell you a lot about what is actually included in the price.